Well, in the last month they’ve basically completed the outside of the house. Observe:
Pretty neat, huh? Now the steps in between:
- 27 April – Three sides are up
- 28 April – Four sides are up
- 28 April – Inside, looking toward the bedrooms on the northwest side
- 28 April – Inside, looking at the fireplace toward the back (southwest) side
- 28 April – Inside, with the fireplace and dining room/kitchen and the quarry lake in the background
- 28 April – Inside, looking at the front door, with the extra bedroom/computer room to the left and the garage to the right
- 3 May – Big cranes setting the roof trusses
- 3 May – Roof trusses in place
- 4 May – “Starting to look like a house now”
- 11 May – Front of the house, from the park
- 11 May – Windows are in, roof is on
- 17 May – Outside is done!